Physical Deployment Process

After completing the floor plan and layout planning, follow these steps for physical anchor deployment:
  1. Site Preparation
    • Verify mounting locations
    • Check power availability
    • Confirm network access
    • Review safety requirements
  2. Equipment Setup
    • Leica Total Station
    • Mounting hardware
    • Network cables
    • Power supplies
    • Safety equipment

Using Leica Total Station

Initial Setup

  1. Position the Total Station at a known reference point
  2. Level and calibrate the instrument
  3. Set up the reference coordinates
  4. Verify line of sight to anchor locations

Coordinate Calculation

  1. Target each anchor location
  2. Record horizontal and vertical angles
  3. Measure distances
  4. Calculate X, Y, Z coordinates
  5. Document measurements
Accurate coordinate measurement is crucial for system performance. Double-check all measurements before proceeding.

Coordinate Documentation

Required Information

  • Anchor ID
  • X, Y, Z coordinates
  • Reference points
  • Installation height
  • Orientation details

Data Format

{
  "anchor_id": "string",
  "coordinates": {
    "x": "float",
    "y": "float",
    "z": "float"
  },
  "reference_point": "string",
  "installation_height": "float",
  "orientation": "degrees"
}

Quality Assurance

Verification Steps

  1. Re-measure key points
  2. Cross-reference with plan
  3. Verify anchor orientation
  4. Test network connectivity
  5. Document final position

Documentation

  • As-built drawings
  • Coordinate sheets
  • Installation photos
  • Network details
For detailed installation guidelines, refer to the Anchor Installation Rules.